507,384 kWh Electricity Saving Annually

360,243 kg CO2 Reduction Annually

14.16% Fan Power Reduction

5,670 kWh Electricity Saving per AHU Annuall

4,026 kg CO2 Reduction per AHU Annually

18.4% Fan Power Reduction

1,549 kWh Electricity Saving per AHU Annually

1,053 kg CO2 Reduction per AHU Annually

17.76% Fan Power Reduction

234 kWh Electricity Saving per AHU Annually

159 kg CO2 Reduction per AHU Annually

5.5% Fan Power Reduction

Reduce ventilation system workload

Reduce infection risk in patient transport cabin

HEPA grade air quality for patients and medical professionals

507,384 kWh Electricity Saving Annually

360,243 kg CO2 Reduction Annually

14.16% Fan Power Reduction

5,670 kWh Electricity Saving per AHU Annuall

4,026 kg CO2 Reduction per AHU Annually

18.4% Fan Power Reduction

1,549 kWh Electricity Saving per AHU Annually

1,053 kg CO2 Reduction per AHU Annually

17.76% Fan Power Reduction

234 kWh Electricity Saving per AHU Annually

159 kg CO2 Reduction per AHU Annually

5.5% Fan Power Reduction

Reduce ventilation system workload

Reduce infection risk in patient transport cabin

HEPA grade air quality for patients and medical professionals

Sun Hung Kai Centre
180 AHUs installed
24-month payback from Capex 507,384 kWh annual
electricity reduction 360,243 kg CO2e Annual Reduction
14.16% Reduction in Fan Power
57.5% Reduction in Pressure Drop
1.65x Increase in PM1 Filtration Efficiency
8.68x Increase in PM2.5 Filtration Efficiency
1.17x Increase in PM10 Filtration Efficiency
30 Harbour Rd, Wan Chai Year of Built:
1981 BEAM Plus Existing Building (Excellent)

EMSD Headquarters
5,670 kWh Annual Electricity Saving for a single AHU
44.4% Increase in PM10 Filtration Efficiencyt
87.4% Decrease in Pressure Drop
18.4% in Fan Power Energy Saving
30 Harbour Rd, Wan Chai Year of Built:
1981 BEAM Plus Existing Building (Excellent)

ONE TAIKOO PLACE
Installed AirSonic TM system in 2021
24 Months Payback
Synergize with VAV control system
11-19% reduction of AHU motor energy use
Taikoo Place, 979 King's Rd, Quarry Bay Year of Built:
2018 Triple Platinum Rating (WELL, BEAM Plus, LEED)

Lincoln House
Installed AirSonic TM system in 2021
1-10% energy reduction depending on fan motor loading
Synergize with VAV control system
Taikoo Place, 979 King's Rd, Quarry Bay
Year of Built:
1998First HKBEAM-awarded building

Ambulance
All HKSAR Government ambulance (450+) vehicles installed AURABEAT Air Handling solution!
OTHER CASE

AG+ Since 2015 | EcoSonic Since 2022

AG+ Since 2015 | EcoSonic Since 2022

AG+ Since 2015 | EcoSonic Since 2022

AG+ Since 2022 | EcoSonic Since 2022

AG+ Since 2022 | EcoSonic Since 2022

AG+ Since 2021

AG+ Since 2021 | EcoSonic Since 2021

AG+ Since 2021

AG+ Since 2021 | EcoSonic Since 2021

AG+ Since 2021 | EcoSonic Since 2021

AG+ Since 2021

AG+ Since 2021
AG+ Since 2015 | EcoSonic Since 2022

AG+ Since 2015 | EcoSonic Since 2022

AG+ Since 2015 | EcoSonic Since 2022

AG+ Since 2015 | EcoSonic Since 2022

AG+ Since 2015 | EcoSonic Since 2022
AG+ Since 2022 | EcoSonic Since 2022

AG+ Since 2022 | EcoSonic Since 2022

AG+ Since 2021

AG+ Since 2021 | EcoSonic Since 2021

AG+ Since 2021

AG+ Since 2021 | EcoSonic Since 2021

AG+ Since 2021 | EcoSonic Since 2021

AG+ Since 2021

AG+ Since 2021